Transnet National Ports Authority (TNPA) has completed a R30 million caisson repair project at the 90-year old Prince Edward Graving dry dock in Durban.
Joanne Castagna via
Joanne Castagna via Wikimedia Commons

Senior engineer Nandi Mtsokoba is leading a team of predominantly female engineers to deliver a world class Durban dry dock facility by the end of 2019, in line with Operation Phakisa. She is the only female in Transnet nationwide that possesses the Government Certificate of Competency (GCC) and is one of only two engineers in the Port of Durban to have this academic qualification in engineering.

The 35-metre long 900-ton outer caisson at the Port of Durban’s Prince Edward Graving Dock has now been commissioned. This was the third and final phase of the TNPA repair programme on the structure, which was deemed unsafe and in need of repair. Work involved structural repairs to the first of two steel lock gates that separate the dock into two compartments and seal off water from the harbour to enable repairs and maintenance work to be carried out on ships serviced at the facility.

Delays

While the outer caisson was handed over to TNPA in December 2015, the commissioning period was longer than planned. “Although the contractors made up for time lost because of an overrun of private repairs on the Africa Mercy ship in August that delayed the start of the caisson repair project, there were further delays towards the end of the project. We thank all our customers for their patience,” said Durban Port manager, Moshe Motlohi.

The project was on schedule for handover to TNPA until the heavy rains late November and early December prevented the contractors from being able to apply the corrosion protection, which is sensitive to weather conditions (wind, rain and humidity).

Once the corrosion protection had been applied, the dry dock was flooded to test the caisson and determine how much ballast was needed to keep it in position. The caisson was then docked at the end of the dry dock so concrete could be pumped into the structure, as soon as suppliers reopened after the festive season shutdown.

Meanwhile the survey vessel WG Magellan, which was booked in for repair, entered the dock in January. Leaks on the vessel delayed its planned exit, causing a further delay to commissioning of the caisson. The concrete-filled caisson was then floated to position, tested and re-docked for minor adjustments before final commissioning.

The outer caisson was put into its operational position on 4 March 2016 and connected to the driving system on 8 March 2016. Thereafter the two tugs and a barge were docked for repair by 10 March 2015.

Future work

The outer caisson repair project is the first of 11 large-scale projects at the dry dock that fall under TNPA’s programme to get the facility into peak condition, in line with Operation Phakisa initiative, which aims to unlock the economic potential of South Africa’s oceans. Under Transnet’s market demand strategy, TNPA will invest around R2 billion over the next five years to refurbish existing repair facilities, together with an estimated R13 to 15 billion to create new repair facilities at the South African ports.

Part of the plan for the Prince Edward Graving Dock includes assessing the inner caisson with a view to its refurbishment, as well as an ongoing caisson maintenance programme to ensure that TNPA gets maximum return on its investment. This would include a concrete refurbishment programme and replacement of cranes and other equipment.

“Congratulations to the TNPA engineering team, contractors Channel Construction, managing contractors Sebata Group and technical advisors Naval Africa - KwaZulu-Natal’s only naval architecture firm - for meeting the challenge of delivering this project and overcoming the numerous hurdles faced along the way,” concluded Motlohi.